Fire remediation measures approved

City Council declares an emergency to speed up a project intended prevent further damage after ground cover was destroyed in September.

November 15, 2012|By Barbara Diamond

The City Council declared a September fire a local emergency so it can take immediate action to prevent the erosion of soil at the site, above Ruby's Diner, which was denuded of vegetation.

On Tuesday, the council voted to spend up to $300,000 for emergency measures recommended by Geofirm to protect the surrounding property during the upcoming rainy season. By proclaiming the interim measures an emergency project, it allows exemption from certain provisions of the California Environmental Quality Act and public contracting provisions that would delay the project.

"Time is of the essence," City Manager John Pietig said.

The post-fire condition of the burn area creates the possibility of rocks, debris and mud cascading onto nearby properties in even a modest rainfall, according to the resolution approved Tuesday.

Advertisement

Pietig will advise the council at the Dec. 4 meeting on bids for the remediation contract and costs to get the process underway as expeditiously as possible.

The Sept. 16 brush fire burned almost 5 acres between Laguna Terrace Park and Nyes Place. Downed power lines were deemed the cause of the fire, according to the fire investigation report by the Laguna Beach Fire Department. Southern California Edison is held responsible by the city.

Remediation measures recommended by Geofirm include debris netting on the upper slope and hydro-seeding.

Laguna Terrace Park will do some of the netting. Almost two-thirds of the burn area is within the park's land, according to information provided by the city. The city owns 4%; the rest is split among nine other owners.

All of the owners have been notified by mail of the city's remediation plan. Two meetings were held to provide them with information and to offer assistance.

The city has sent an agreement to the property owners, asking for permission to go onto the properties to carry out the remediation and asking for reimbursement of the costs if payment is not forthcoming from Edison.