Advertisement

City will slow down Village Entrance Project

Council plans to also seek more public input.

February 06, 2014|By Bryce Alderton

Laguna Beach City Council members acknowledged Tuesday the importance of moving ahead with the Village Entrance Project, albeit at a slower pace and with more public input.

The council voted 5 to 0 to pay KDM Meridian, a land surveying company, $28,300 to develop a map outlining the Village Entrance site area and accept proposals from designers, landscape architects, civil engineers and environmental consultants. The plan calls for a landscaped pedestrian pathway.

In a related matter, council members, echoing public testimony, differed on what should be done with the historic building used to store police evidence near the parking lot at Forest Avenue and Laguna Canyon Road.

Advertisement

Staff recommended spending up to $300,000 to renovate the building's exterior — including upgrading rickety stairways — and using an additional $1 million originally slated for the structure to renovate a median that bisects Laguna Canyon Road. The council did not approve those requests Tuesday night.

The structure known as the former sewer building is part of Laguna's historic resource inventory, meaning the building has strongly maintained its original integrity and demonstrates a particular architectural style or time period, a city staff report said.

Residents supported its preservation.

"I am dismayed at the (repetition) with which we seem to be talking about destroying what's left of old Laguna. We don't have very much left," resident Bonnie Hano said. "It is incumbent upon us to try to preserve these old buildings."

Larry Bammer, president of the Laguna Beach Police Employees Assn., called the condition of the old sewer building "deplorable" and said the $1 million should be used to rehabilitate the facility for the one city employee who enters the structure daily for work.

"There are no plans to move [evidence] to a different location," Bammer said. "We have exceeded the storage capabilities within the Police Department."

Bammer referenced the $1.3 million that city staff budgeted to turn the building into a visitors' center as part of the previous Village Entrance plan, which included a parking structure and came with an expected cost of $42.3 million. The council voted in November for a scaled-down project without multilevel parking.

Staff estimates that the revised project would cost $14.4 million.

Coastline Pilot Articles Coastline Pilot Articles
|
|
|